Critical Infrastructure
Genesis IWS Anderson Phase 2











LocationAnderson, SC
Project Size~ 40,000 SF mining yard | 6 MW capacity
Engineer/ArchitectN/A
Genesis IWS Anderson Phase 2 Phase 2 expanded the Genesis crypto mining campus with a new 6 MW pod yard, complete site preparation, and medium voltage infrastructure to support high density computing operations.
- Stripped topsoil over ~40,000 SF and installed surge-stone entrance tying into the existing asphalt lot
- Furnished and placed stone base for the new mining yard
- Installed medium-voltage (12.7 kV) primary cabling, grounding grid, yard lighting, and emergency-power circuits
- Set four owner-supplied 2,500 kVA pad-mounted transformers
- Placed sixty owner-provided 8 ft x 8 ft x 8 in prefabricated concrete pads
- Transported and installed forty-eight owner-furnished crypto-mining pods onto pads
- Erected 880 LF of 7-ft chain-link fence with barbed-wire and razor-wire topper for site security