Special thanks to our trade partners for assisting Langston in completing another industrial shut down project. This project required one 275T crane and one 400T crane to remove and reinstall a piece of industrial equipment without impacting the existing building structure. The project required 3 months’ worth of planning, 2 weeks of onsite pre-work, 6 days of continuous work efforts including 24 hours shifts, 2 days of equipment startup/testing, and one week of post startup work. Langston and the trade teams worked feverishly to bring this project in 2 days ahead of scheduled completion with a focus on ZERO UNSAFE BEHAVIOURS.